1987Company established as MITCORR SERVICES-
1987Hazira–Bijapur–Jagdishpur Pipeline: installation of anodes and test lead pointsGAIL (India) Ltd
1988GNFC Bharuch: survey, design, supply, installation & commissioning of 2 ICCP stations for PCB plant pipingGNFC, Bharuch
1989TCP by sacrificial CP system for 13 km raw water pipeline, Gujarat Refinery, BarodaGujarat Refinery (IOCL)
1990Supplementary CP System: 12 TR Units, 216 anodes, 36 semi-deep well anode beds; KRIBHCO HaziraKRIBHCO, Hazira
1990Maintenance and modification of 26 CP stations and 427 TLPsGNFC, Bharuch
1991Survey, design, supply, installation & commissioning of 3 CP stations and remote ground beds for gas pipelineGujarat Gas Co. Ltd, Surat
1991ICCP System: design, supply, installation & commissioning for 11 km gas pipelineGujarat Gas Co. Ltd, Surat
1992Design, supply, installation & commissioning of ICCP system for 15 km gas pipelineGujarat Gas Co. Ltd, Surat
1993Supply and installation of sacrificial anode CP system for RSEB PipelineGAIL (India) Ltd
1993Design, installation & commissioning of ICCP System: Desu–Bahadurgarh–Sonepat Spur line, 10 kmGAIL (India) Ltd
1993Monitoring & maintenance of ICCP system: gas pipelines, Baroda & AhmedabadGAIL (India) Ltd
1995Temporary sacrificial anode system for 18" dia, 64 km NTPC–Gandhar pipelineGAIL (India) Ltd
1995ICCP System: Desu–Sonepat–Bahadurgarh pipeline, 3 CP stationsGAIL (India) Ltd
1996Monitoring & maintenance of ICCP system: GAIL Baroda gas pipelineGAIL (India) Ltd
1996ICCP System for underground piping: Acetic Acid plant, GNFC BharuchGNFC, Bharuch
1997Temporary CP by sacrificial anode system for 162 km HBJ (GREP) pipelinesGAIL (India) Ltd
1997ICCP System: 63 km Gandhar–Zanor NTPC gas pipelineGAIL (India) Ltd
1997ICCP System for 2 steel tankage: Indian Oil Corporation, KandlaIOCL
1998ICCP of 162 km HBJ (GREP) pipelineGAIL (India) Ltd
1998Temporary CP by sacrificial anode system for 251 km Mumbai–Manmad pipelineBPCL
1998Design, supply & installation of ICCP system for SGGU project plant piping, GNFC BharuchGNFC, Bharuch
1999ICCP System for 251 km Mumbai–Manmad pipeline: CPPSM-8, TRU-3, deep well & shallow anode beds; EHT & DC traction interference survey & mitigationBPCL
1999ICCP System for 50 km Neepco–TSED gas pipeline, Tripura: 3 TR units & 3 deep well anode bedsGAIL (India) Ltd
1999ICCP system for piping at Bareja pump stationIOCL
2000Monitoring and maintenance of ICCP: GAIL gas pipelines, Baroda regionGAIL (India) Ltd
2001CP by sacrificial anode system for GAIL gas pipelineGAIL (India) Ltd
2001ICCP System: Ammonia plant, GNFC BharuchGNFC, Bharuch
2001Monitoring of ICCP system: GAIL gas pipelines, NoidaGAIL (India) Ltd
2001TCP by sacrificial anodes for Kakinada–NFCL pipeline: 14"×63 km Tatipaka–Narsapur; 12"×63 km Narsapur–KovvurGAIL (India) Ltd
2001ICCP System: GGCL SE Ankleshwar gas pipelineGGCL, Ankleshwar
2001ICCP System: GGCL Garden Vareli Distribution project gas pipelineGGCL, Surat
2001TCP for 11 km gas pipeline: Indraprasth Gas Ltd, New DelhiIGL, New Delhi
2001ICCP System for gas pipeline: RAVVA gas field, Cairn Energy, ChennaiCairn Energy India Pvt Ltd
2002TCP by sacrificial anode + ICCP (TRU System) for 10.9 km pipeline: IOCL Gujarat Refinery, Dumad; 2 TRS, 2 MMO deep well anode bedsIOCL
2002ICCP System for GAIL gas pipeline to Haryana Sheet GlassGAIL (India) Ltd
2002ICCP System: MORA–RELIANCE–NTPC gas pipelineGGCL, Surat
2002Maintenance of ICCP System: GAIL gas pipelines, Bharuch regionGAIL (India) Ltd
2003TCP by sacrificial anodes & ICCP (TRU system) for 45 km Amboli–Dahej pipeline, GSPLGSPL, Gandhinagar
2003Monitoring & maintenance of ICCP: GAIL Baroda & Bharuch regionGAIL (India) Ltd
2003Quarterly monitoring & maintenance of CP System: LPG pipeline, Jamnagar jurisdictionGAIL (India) Ltd
2003CIPL Survey (ON/OFF potential) for 4 km pipeline, Hazira regionClough Engineering Ltd, Surat
2003Soil resistivity survey for proposed onshore pipeline at Hazira, Surat (Niko Resources)Clough Engineering Ltd
2003ICCP groundbed design & commissioning: CNG UdhanaGGCL, Surat
2003CP design review of design by John Brown TechnologiesClough Engineering Ltd
2003Cathodic protection of Hydrogen lineIndu Nissan Oxo Chemical Industries Ltd, Vadodara
2003Deep well anode bed installation at Viramgam/Rajkot: SMPL PipelineTitanor Components Ltd, Goa
2003CP system for North Balol FieldHindustan Oil Exploration Company Ltd (HOEC), Vadodara
2003Rate contract: test stations, CP cable, permanent reference cells, zinc grounding cells, MMO anodes along HBJ pipeline (125 km)GAIL, Jhabua (MP)
2003ICCP System for steel piles: Petronet LNG Jetty Project, DahejCorrpro Corrosion Control India (Pvt) Ltd, Mumbai
2003TCP/PCP for steel grid distribution network: Nandesari & Alembic SectionGujarat Adani Energy Ltd, Ahmedabad
2003TCP and permanent CP system for Mundra–Kandla Pipeline (MKPL)IOCL
2004Design, engineering, procurement, fabrication, installation, testing & commissioning: offshore and onshore platforms and pipelinesClough Engineering Ltd, Australia
2004CP system for IOCL Panipat–Rewari pipeline projectJai Hind Projects Limited, Ahmedabad
2004Detail engineering, procurement, installation, testing & commissioning of ICCP for underground pipingKirloskar Brothers Ltd, Pune
2004TCP & PCP works for GACL–Petronet Dahej Pipeline Project (GSPL)GSPL
2004TCP & PCP works for LPG Pipeline: Gujarat Refinery to Dumad TerminalIOCL
2004PCMS, CIPS & remedial measures: JNPT–VASHI Pipeline ProjectIOCL, Mumbai
2005CP system design & installation for Fire Water PipelineSaint-Gobain Glass India Ltd, Chennai
2005Sacrificial anode type CP System for GAIL Ujjain pipelineGAIL (India) Limited, Ujjain
2006CP system for GGCL Vapi LDZ Natural Gas Pipeline ProjectGujarat Gas Company Ltd, Surat
2006CP for GSPL Spur Pipelines, VapiGSPL
2006Monitoring & maintenance of CP System: pipelines at Hazira regionONGC, Mumbai Region
2006CP work for steel pipeline network: Kanpur City Gas Distribution (GAIL/CUGL)Ario Brothers
2006Installation, testing & commissioning of SACP: Reliance Petroleum, JamnagarReliance Petroleum Limited, Jamnagar
2006TCP and PCP for condensate pipeline: VAP-Mini Refinery Project, ONGC KhutalamNicco Corporation Ltd, Kolkata
2006Soil resistivity survey: water pipeline from Almatti to JSW Plant, Vidya NagarJMC Projects (India) Ltd, Mumbai
2007–2008CP work for CNG pipeline 4" & 8": Express Highway (Halol) to GSRTC Race Course, VadodaraArio Brothers, Vadodara
2007–2008Permanent CP work for Chandkheda–Motera Gas Pipeline Project, GSPC GasAneri Constructions, Surat
2007–2008CP works for IOCL combined works project, NagapattinamIOCL
2007–2008Installation of polarised cell at HT crossings, permanent reference cell and data loggers: HVJ PipelineGAIL (India) Limited, Ujjain
2007–2008Replacement of TR Units: 42" SBHT and 16" KRIBHCO pipelines ICCP, Hazira regionONGC, Mumbai Region
2007–2008TCP/PCP for ATF Pipeline: CPCL Manali Refinery to Chennai AFSIOCL
2007–2008TCP and PCP for GSPL Spur Pipelines, VapiGSPL
2007–2008CP works for cooling water & make-up water system: Barh STPP (3×660 MW), BiharNTPC
2009CP system for 4×125 MW Kosti Thermal Power Plant, Sudan (international project)Bharat Heavy Electricals Ltd (BHEL)
2009CP maintenance: Jamnagar Maintenance BaseGAIL (India) Ltd
2009CP for 4" dia steel pipeline network: Surendranagar extension (9 km)GSPC
2009CIPL-DCVG Survey for pipelines under RPNHQ, VadodaraGAIL (India) Limited
2009CP system for Kondapalli spur pipe project, Reliance (12 km)Reliance Gas Transportation Infrastructure Ltd
2009CP system for station piping package: Simhadri Super Thermal Power Project Stage II (2×250 MW)NTPC
2009TCP work for Dahej–Vijaipur Pipeline Phase II, Spread I (145 km)GAIL (India) Ltd
2009AMC of ICCP system: charged pipeline at KanpurCUGL
2010CP for Surendranagar extension steel pipeline networkGSPC
2010CP system for Kondapalli spur pipe project, RelianceReliance Gas Transportation Infrastructure Ltd
2010Cathodic protection for Enppi project, EgyptPolcon Equipments Ltd
2010AMC of ICCP system: charged pipeline at KanpurCUGL
2011Installation of deepwell anode bed, TR unit & auxiliaries (×2 work orders)GAIL (India) Ltd
2011CIPL-DCVG Survey for pipelines under RPNHQ, VadodaraGAIL (India) Ltd
2012CP for crude unloading at Karaikal Port (KPPL), NagapattinamNRP Projects Pvt. Limited
2012Supply & installation of TCP & PCP works for City Gas Distribution project, KotaGAIL Gas Ltd, Kota
2012Supply, installation & commissioning of 10 polarisation cells in Tamil NaduPetronet CCK Ltd
2012CP maintenance: Jamnagar Maintenance BaseGAIL (India) Ltd
2012Installation of new CP stations and associated work for GAIL pipelinesGAIL (India) Ltd
2013Erection & commissioning of CP system for 1×350 MW Hazira CCPPBharat Heavy Electricals Ltd (BHEL)
2013Supply & installation of anodes for CP of pipelines, KakinadaBhagyanagar Gas Ltd
2013Hiring of services: survey of 8" Crude Oil Trunk Pipeline, ONGC Odalarevu to S. YanamONGC
2013AMC of CP system for GSPC Gas steel pipeline network, Gujarat (120 km)GSPC Gas Co. Ltd
2013AMC for CP system under RPNHQ, Vadodara–Bharucha regionGAIL (India) Ltd
2013Monitoring & maintenance of CP system: pipelines at Hazira regionONGC
2014Supply & installation of anodes for CP of pipelines, KakinadaBhagyanagar Gas Ltd
2014Monitoring & maintenance of CP: Hazira HNG (O&M)HNG, Hazira
2014TCP system for IOCL SMPL Debottlenecking project Group C & EIOCL
2014CIPL survey at Rajkot baseSanmarg Projects Pvt. Ltd
2015AMC of CP system for GSPC Gas steel pipeline network, Gujarat (120 km)GSPC Gas Co. Ltd
2015TCP for GSPL Silvasa & China Steel ProjectAneri Construction Pvt. Ltd
2015Supply & installation of cathodic protection for GAIL BangaloreKrita Engineering (P) Limited
2015TCP system works for Salaya–Mathura Pipeline: river crossings by HDDIOCL
2015PCP design, survey and final bonding: China Steel Dahej & GSPC Jamnagar projectsAneri Construction Pvt. Ltd
2015TCP works at UP and West Bengal for HDD: IOCL HB-HMR-BK ProjectGypsum
2015Survey of 6" well fluid pipeline from landfall point to ONGC OdalarevuONGC
2016AMC for CP system under RPNHQ, Vadodara–Bharucha region-2GAIL (India) Limited
2016TCP work at IOCL project: AIE River, Bongaigaon, AssamIOCL
2016TCP system works for Salaya–Mathura Pipeline: river crossings by HDD (continued)IOCL
2016External Corrosion Direct Assessment Survey of VSPL for Vizag, G Konduru & Cherlapalli Region: 613 kmGAIL (India) Ltd
2016Koyali–Viramgam Pipeline (KVPL) Replacement Project: TCP & PCP works, 157 kmIOCL
2017Mainline CP works as per IOCL specification: 42" dia mainline from Chennai Port Trust to CPCL Refinery R&D Gate, ManaliIOCL
2018AMC for CP system of pipeline under GAIL RPNHQ, Vadodara: Region II, Undera (2 years, 450 km)GAIL (India) Ltd
2018AMC & Annual Rate Contract for O&M of CP system: various Sabarmati Gas Limited locations, Zone 1Sabarmati Gas Ltd
2020Annual Rate Contract for CP system: Region 1 (Undera), 2 years, 450 kmGAIL (India) Ltd
2020Cathodic protection system for Spread B, Assam: 190 kmOil India Limited
2020AMC of CP system at Indore, Ujjain & Gwalior: City Gas Distribution project, 90 kmAavantika Gas Ltd
2021Design, supply, installation, testing & commissioning of PCP & TCP system for 2 nos. 16" dia UG pipeline: SRPL Pumping Station to IOCL Marketing Terminal, Asanur, Tamil Nadu (2 km)IOCL
2022CP for Ethylene line: PCP design, site survey, material supply, as-built drawings, FLP test station installation (5 nos.) & thermit welding cables; Gulbrandsen Speciality Chemicals, Dahej (0.5 km)Gulbrandsen Speciality Chemicals LLP
2023TCP & PCP system: design, supply, installation & testing for 14" IOCL CTMPL Rerouting Pipeline (5.5 km)IOCL
2023Mainline laying and composite station works: 12.75" OD, 38 km natural gas pipeline from Thiruvallur to Sri City (ETBPNMTPL Project)IOCL
2023CP for 3 nos. underground pipelines (20", 16" & 14" dia, 4.5 km each): Vizag Port to BPCL Vizag Installation ProjectBPCL
2023Mainline laying and HDD for rerouting of 10.75" OD JVPL: tie-in & hook-up, IPS defect repair and CP system renovation (18 km)IOCL
202316" OD mainline: Baithkol to Karwar Naval Base (10 km)IOCL
2023CP surveys for 24 RLNG Project: CIPL On/Off (242 km), DCVG (121 km), AC interference (121 km) & mutual interference (121 km) surveysIOCL
2023Tank bottom CP work: 9 nos. fuel storage tanks, IOCL Mundra ProjectIOCL
2024Design, supply, installation & commissioning of PCP & TCP system: Lucknow International Airport (4 km)IOCL